The status for technology for the summer of 2017 will be posted here.  Please check back for updates.

 

Project / Large Impact Considerations

District-wide:

  • Wireless will be available all summer.
  • All teacher stations will be being replaced and not available until complete.
  • Admin stations will be being replaced – you will be contacted for any downtime/schedule replacements.
  • Laptop carts will be taken and secured for the summer.  They will be redistributed during the first week of school.

JSHS:

  • Desktops/rooms at the JSHS will not be available for the majority of the summer due to a infrastructure wiring project.  This includes the 118 lab, 145 LMC, and 216 lab.

MES:

  • Desktops/rooms at MES will be on the normal availability schedule, check the lists below for individual room completion.
  • The lab will be available for use throughout the majority the summer.

BBC

  • Desktops/rooms at BBC will be on the normal availability schedule, check the lists below for individual room completion.

 

JSHS Room Status

Room  Expected Completion Date  Status
H-112
8/8/17
Pending new machine
H-114 Lab
8/22/17
Pending re-wire
H-116
8/8/17
Pending furniture
Pending re-wire
Pending new machine
H-118 Lab
8/22/17
Pending furniture
Pending re-wire
Pending new machine
H-109
8/8/17
Pending re-wire
Pending new machine
H-111
8/15/17
Pending new machine
H-LMC
8/8/17
Pending re-wire
Pending new machine
H-145D
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-122
8/8/17
Pending re-wire
Pending new machine
H-124
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-125
8/8/17
Pending re-wire
Pending new machine
H-126
8/8/17
Pending re-wire
Pending new machine
H-128
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-131
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-132
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-133
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-140
8/8/17
Pending re-wire
Pending new machine
H-142
8/8/17
Pending re-wire
Pending new machine
H-144
8/8/17
Pending re-wire
Pending new machine
H-146
8/8/17
Pending re-wire
Pending new machine
H-148
8/8/17
Pending re-wire
Pending new machine
H-136D
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-136B Lab
8/15/17
Pending Summer School End
Pending re-wire
Pending new machine
H-137B
8/8/17
Pending re-wire
Pending new machine
H-204
8/8/17
Pending re-wire
H-206
8/8/17
Pending re-wire
Pending new machine
H-210
8/8/17
Pending re-wire
H-212 & (A,B,C)
8/8/17
Pending re-wire
H-214
8/8/17
Pending re-wire
Pending new machine
H-215
8/8/17
Complete
H-216 Lab
8/22/17
Pending re-wire
H-220
8/8/17
Pending re-wire
H-221
8/8/17
Pending re-wire
H-222
8/8/17
Pending re-wire
H-223
8/8/17
Pending re-wire
H-224
8/8/17
Pending re-wire
H-226
8/8/17
Pending re-wire
H-227
8/8/17
Pending re-wire
H-228
8/8/17
Pending re-wire
H-229
8/8/17
Pending re-wire
H-230
8/8/17
Pending re-wire
Pending new machine
H-231
8/8/17
Pending re-wire
Pending new machine
H-232
8/8/17
Pending re-wire
Pending new machine
Pending projector replacement
H-233
8/8/17
Pending re-wire
Pending new machine
H-234
8/8/17
Pending re-wire
Pending new machine
H-241
8/8/17
Pending re-wire
Pending new machine
H-240
8/8/17
Pending projector install
Pending re-wire
Pending new machine
H-243
8/8/17
Pending re-wire
Pending new machine
H-244
8/8/17
Pending re-wire
Pending new machine
H-247
8/8/17
Pending re-wire
Pending new machine
H-248
8/8/17
Pending re-wire
Pending new machine
H-204
8/8/17
Pending re-wire
Pending new machine
H-MPR
8/15/17
Pending smartboard install
Pending re-wire
Pending new machine

MES Room Status

Room  Expected Completion Date  Status
E-200
8/16/17
Pending new machine
E-201
8/16/17
Pending new machine
E-203
8/16/17
Pending new machine
E-248
8/16/17
Pending new machine
E-205
8/16/17
Pending new machine
E-207
8/16/17
Pending new machine
E-247
8/16/17
Pending new machine
E-206
8/16/17
Pending new machine
E-209
8/16/17
Pending new machine
E-208A
8/16/17
Pending new machine
E-208B
8/16/17
Pending new machine
E-211
8/16/17
Pending new machine
E-210
8/16/17
Pending new machine
E-213
8/16/17
Pending new machine
E-214
8/16/17
Pending new machine
E-215
8/16/17
Pending new machine
E-216
8/16/17
Pending new machine
E-217
8/16/17
Pending new machine
E-218
8/16/17
Pending new machine
E-219
8/16/17
Pending new machine
E-Lab
8/16/17
Pending new machine
E-238
8/16/17
Pending new machine
E-222
8/16/17
Pending new machine
E-224
8/16/17
Pending new machine
E-226
8/16/17
Pending new machine
E-227
8/16/17
Pending new machine
E-228
8/16/17
Pending new machine
E-229
8/16/17
Pending new machine
E-230
8/16/17
Pending new machine
E-231
8/16/17
Pending new machine
E-100
8/16/17
Pending new machine
E-102
8/16/17
Pending new machine
E-104
8/16/17
Pending new machine
E-106
8/16/17
Pending new machine
E-112
8/16/17
Pending new machine
E-114
8/16/17
Pending new machine
E-116
8/16/17
Pending new machine
E-118
8/16/17
Pending new machine
E-120
8/16/17
Pending new machine
E-122
8/16/17
Pending new machine

BBC Room Status

Room  Expected Completion Date  Status
B-100
Complete
Complete
B-101
Complete 
Complete
B-104
Complete 
Complete
B-201
Complete 
Complete
B-203
Complete 
Complete
B-301
Complete 
Complete
B-303
Complete 
Complete

 

Was this article helpful to you?